| Project Milestone | Description (Days from Appointed Date) | Planned | Achieved Actual | Current Physical Status | ||
|---|---|---|---|---|---|---|
| Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | |||
| Project Milestone-I | 160 | 20% | 03-Sep-24 | |||
| Project Milestone-II | 360 | 35% | 20-Jun-25 | |||
| Project Milestone-III | 500 | 75% | 07-Nov-25 | |||
| Schedule Completion | 730 | 100% | 27-Mar-26 | |||